Wildlife transfer Neuenkirch, Luzern

2021

In Neuenkirch, the Federal Roads Office FEDRO is already building the second wildlife bridge with a wooden overpass after the Rynetel wildlife bridge. The wildlife overpass in the canton of Lucerne has a width of 50 meters and a length of around 36 meters.

Facts and images
Construction Data
Involved
Articles
Assembly work with single lane traffic
Assembly work with single lane traffic
The second lane is covered
The second lane is covered
The girders weigh about eight tons...
The girders weigh about eight tons...
...and are placed in one piece on the concrete foundations.
...and are placed in one piece on the concrete foundations.

The project
During several nights carpenters assembled the 17.5 meters long, 1.24 meters high and 8 tons heavy wooden girders. In the future, deer, foxes, stags and small mammals will walk across the new wildlife bridge near Neuenkirch. This pleases the environment in various ways. Because the wildlife bridge is a real CO2-reservoir. Around 2,500 cubic meters of wood, mostly spruce from the Entlebuch region, are being used to build it. The fact that the wood was cut in the surrounding forests and processed in regional companies is a benefit for the local economy. The environment is also pleased. After all, from an ecological point of view, local wood is clearly more advantageous than wood from abroad.

The construction
The wildlife overpass in the canton of Lucerne has a width of 50 meters and a length of about 36 meters. The clear height is 4.80 meters. The almost man-high glulam beams were prefabricated at n'H in Lungern, pre-assembled and delivered to the construction site just in time.

The challenge
Even during the assembly of the girders, traffic continued to roll. For around 30 nights, traffic was directed in opposite directions on a single lane. During the day, two lanes were always available in each direction.

Construction Data

- Width 50 meters

- Length 36 meters

- Clear height 4.80 meters

- 2500 m3 Spruce wood from the region


Construction costs

- BKP 1-9: 10.7 million Swiss francs

- BKP 214: approx. 2.7 million francs

- Planning fee: 198'000.Franken (as subplanner of the civil engineer)


Services of Timbatec

- SIA Phase 31 Preliminary design

- SIA Phase 32 Construction project

- SIA Phase 41 Tendering and comparison of offers

- SIA Phase 51 Implementation project

- SIA Phase 52 Execution

- SIA Phase 53 Commissioning

- Structural analysis and design

- Cost estimation

- Technical site supervision and site inspections

Owner
Federal Roads Office ASTRA
4800 Zofingen


Timber construction engineer
Timbatec Holzbauingenieure (Schweiz) AG Bern
3012 Bern


Timber construction
HUSNER AG Holzbau
5070 Frick


Civil engineer
IG 2B Ingenieurgemeinschaft
3000 Bern 15


GU/TU
Anliker AG
6021 Emmenbrücke


Datenschutzhinweis

Diese Webseite nutzt externe Komponenten welche dazu genutzt werden können, Daten über Ihr Verhalten zu sammeln.

Notwendige Cookies werden immer geladen