The project
On the part of the building along the Weststrasse, which was topped up with apartments, the timber construction is realized in a classic frame construction with a hollow box roof. The extension on the side facing Birmensdorferstrasse is largely column-free and self-supporting to allow the most flexible office use possible.
The construction method
Only in the ridge-valley diagonal, in order to be able to maintain the joist-free appearance, two supports had to be introduced. Otherwise, the addition is designed as a blast structure, with the two roof sides functioning as "struts" and the roof slice as a "compression beam". The loads for the overall bracing are transferred via the roof slice into the fire walls as well as the massive stairwell with elevator.
Construction Data
- 350 m2
- 450 m2
Services of Timbatec
- SIA phase 32 construction project
- Structural analysis and design
- SIA Phase 41 Tendering and comparison of offers
- SIA Phase 51 Implementation project
- Site management and site inspections
General Contracting
Allreal Generalunternehmung AG
8050 Zurich