New construction of a roof for the Brünnli ice rink, Hasle b. Burgdorf

2005

A roof for the previously open ice rink was to be built over the existing civil defense facility. The building lines allowed hardly any leeway in the design of the roof shape. Limitations had to be observed not only in the ground plan, but also in the section.

Facts and images
Construction Data
Involved
Aerial view
Aerial view
View of the base components
View of the base components
Setting up the binder
Setting up the binder
Binder
Binder
Detail
Detail

The project
The aforementioned constraints led to the chosen structural form with a truss spacing of 5.20 - 7.00 m.

The construction method
The trusses are designed as an underbraced, buckled 3-hinged frame, which is additionally extended on one side by a post and bracing. This allows the bending moments in the stem to be reduced. The secondary structure consists of rafter purlins designed as Gerber girders. The trusses stand on clamped steel supports; the roofing was made of corrugated sternite.

Construction Data

- Total 260 m3 Wood

- Hall: 48 x 60 m

- Height ridge: 13.6 m

- Useful area: 2'880 m2


Services of Timbatec

- Condition analysis

- Inspection and monitoring

Timber constructioncontractors
Zimmerei Kühni AG
3435 Ramsei


Timber construction engineers
Timbatec Holzbauingenieure Schweiz AG, Thun
3600 Thun


Engineering Office Foundations
Kohler und Schöni Ingenieure AG
3415 Hasle


Client
Sportbetriebe Brünnli AG
3415 Hasle-Rüegsau